Undershelf rebuild update

Both platforms are now in place & wired up, the signals have been moved to their final positions & wired back up and the road bridge has been refitted. All that is left to do now is a little more fencing on platform 1, a wall at the far end of platform 1 & to remake the banking around the bridge.